Error: "A scheduled "Work To Do" took over one minute to be run".

(Last modified: 22Oct2002)

This document (10021510) is provided subject to the disclaimer at the end of this document.

fact

Novell NetWare 4.11

Novell NetWare 4.11 Support Pack 7A (NW4SP7A.EXE)

symptom

Error: "A scheduled "Work To Do" took over one minute to be run".

Restore operation receives error

Console locks up for 5 or 10 minutes

cause

This problem occurs when a process takes more than one minute on the processor creating a bottleneck problem.  This error can also be accompanied by CPU HOG Timeout abends.  Any NLM that takes over control of the processor and will not relinquish it can cause this type of problem.  When dealing specifically with backups, many problems stem from the disk channel itself.

fix

Check the disk/tape channel (drivers, BIOS revisions, cables, and hardware).

document

Document Title: Error: "A scheduled "Work To Do" took over one minute to be run".
Document ID: 10021510
Solution ID: 1.0.37608857.2390167
Creation Date: 11Nov1999
Modified Date: 22Oct2002
Novell Product Class:NetWare

disclaimer

The Origin of this information may be internal or external to Novell. Novell makes all reasonable efforts to verify this information. However, the information provided in this document is for your information only. Novell makes no explicit or implied claims to the validity of this information.
Any trademarks referenced in this document are the property of their respective owners. Consult your product manuals for complete trademark information.